HomeMy WebLinkAboutBid Tabulation Seminary Mulberry lotCITY OF GALESBURG
Purchasing
Operating Under Council- Manager Government Since 1957
SEMINARY MULBERRY PARKING LOT
BIDDER NAME:
Section: 22-01201-58-PK BIDDER ADDRESS:
Bid Date: 7/6/2022 CITY/STATE/ZIP:
ATTENDED BY: MILLER/GAVIN
UNIT UNIT UNIT
QTY UNIT ITEM PRICE TOTAL PRICE TOTAL PRICE TOTAL
14 CY TRENCH BACKFILL 80.00$ 1,120.00$ 63.00$ 882.00$
830 SY GEO FAB FRO GROUND STAB 3.00$ 2,490.00$ 3.49$ 2,896.70$
22 SY AGG BASE CRSE, TY B, 2"25.00$ 550.00$ 53.12$ 1,168.64$
505 SY AGG BASE CRSE, TY B, 2" SPL 11.00$ 5,555.00$ 9.48$ 4,787.40$
21 SY AGG BASE CRSE, TY B, 6"16.00$ 336.00$ 60.72$ 1,275.12$
830 SY AGG BASE CRSE, TY B, 8"25.00$ 20,750.00$ 35.00$ 29,050.00$
302 LBS POLY BIT MATLS (TACK COAT)7.00$ 2,114.00$ 7.28$ 2,198.56$
71 TON POLY HMA BIND CRSE IL 9.5 420.00$ 29,820.00$ 441.25$ 31,328.75$
71 TON POLY HMA SURF CRSE MIX D N50 420.00$ 29,820.00$ 441.25$ 31,328.75$
22 SY PCC DRIVEWAY PVT, 8"195.00$ 4,290.00$ 409.54$ 9,009.88$
385 SF PCC SIDEWALK, 5"37.00$ 14,245.00$ 24.06$ 9,263.10$
120 SF PCC SIDEWALK, 8"39.00$ 4,680.00$ 72.59$ 8,710.80$
8 SY PAVEMENT REMOVAL 32.00$ 256.00$ 458.55$ 3,668.40$
73 FT CURB REMOVAL 20.00$ 1,460.00$ 52.79$ 3,853.67$
700 SF SIDEWALK REMOVAL 6.00$ 4,200.00$ 10.66$ 7,462.00$
48 FT STORM SEWER CL B, TY 1, 12"124.00$ 5,952.00$ 157.90$ 7,579.20$
1 EA INLETS, TY A, TY 5 F&G OL 3,980.00$ 3,980.00$ 11,002.91$ 11,002.91$
326 FT CONC CURB, TY B 98.00$ 31,948.00$ 56.52$ 18,425.52$
1 LS MOBILIZATION 5,000.00$ 5,000.00$ 7,501.71$ 7,501.71$
1 LS TRAFFIC CON & PROT (SPL)3,900.00$ 3,900.00$ 4,502.47$ 4,502.47$
1 LS CONSTRUCTION LAYOUT 2,500.00$ 2,500.00$ 6,689.94$ 6,689.94$
1 LS TOPSOIL, EX. AND PLACE 5,400.00$ 5,400.00$ 4,871.57$ 4,871.57$
1 LS LANDSCAPING 14,000.00$ 14,000.00$ 7,015.19$ 7,015.19$
484 CY EARTH EXCAVATION 35.00$ 16,940.00$ 52.33$ 25,327.72$
-$ -$
-$ -$
TOTAL COST 211,306.00$ 239,800.00$
Laverdiere Construction Otto Baum Company, Inc.
4055 W. Jackson Street 866 N. Main St.
Bid Bond Bid Bond
Macomb, IL 61455 Morton, IL 61550