HomeMy WebLinkAbout20240124 - Hawthorne Phase 2 - Bid TabOWNER NAME:Bid Date:
Bid Location:
Bid Time:
Project No.:
MSI
Valley
Construction CAD Construction Bishop Bros Hein Construction
X X X X X
X X X X X
X X X X X
X X NONE NONE NONE
$1,368,712.00 $1,399,000.00 $1,280,000.00 $1,340,000.00 $1,243,000.00
$219,460.00 $361,300.00 $370,000.00 $239,000.00 $291,000.00
$72,000.00 $70,485.00 $135,000.00 $69,000.00 $178,000.00
Deduct $103,436.00 NONE NONE Deduct $109,000.00 NONE
$1,588,172.00 $1,760,300.00 $1,650,000.00 $1,579,000.00 $1,534,000.00
Respectfully Submitted By:
January 26, 2024
Project Manager Date
Klingner & Associates, PC
Addenda Acknowledged
Contractor
BID TABULATION
Total (Including Alternate #1)
Contractor Suggested Schedule
Submitted
Cody N. Basham
Bid Bond or Certified Check
Alternate #1 - Boiler Replacement:
Abate and remove existing boiler and
associated boiler components and
Alternate #2 - Paint Entire Pool
Ceiling: Paint entire wood deck boads
in Pool area in lieu of previously
replaced bare wood deck boards
Contractor Suggested Alternate
Base Bid w/ Contingencies
Contractor Qualifications Statement
QUINCY ∙ GALESBURG ∙ BURLINGTON ∙ PELLA ∙ DAVENPORT ∙ HANNIBAL ∙ COLUMBIA ∙ DAVENPORT∙ CARBONDALE
Wednesday, January 24, 2024
City Hall - Erickson Conference Room
11:00am
23-3054
City of Galesburg
Hawthorne Pool - Phase 2 RenovationPROJECT NAME:
www.klingner.com