HomeMy WebLinkAboutBid Tabulation Golf Cart Path ResurfacingCity of Galesburg
Finance Department
Bid Opening: Bunker Links Golf Cart Path Installation and Resurfacing
Bid Date: 09/24/2025
Bid Time: 11:00 AM
Attended by: T.Miller / D.Miles
Bidder
City, State
Unit Price Extension Unit Price Extension Unit Price Extension
Base Bid:
Cost per Square Yard of Finished Cart Path
(approximately 534 square yards of hot mix and
approximately 400 square yards of CA-6 rock)176.00 93,984.00 82,900.00 82,900.00
Alternate Bid:
Cost per Square Yard of Finished Cart Path
(approximately 267 square yard of hot mix)110.00 29,370.00 155.00 41,385.00
Bid Guarantee:
Anticipated Start Date:
Anticipated Completion Date:
Bids are currently under review by City staff.
Bid Bond
10/20/2025
10/29/2025
Bid Bond
14 Days from NTP
10 Working Days
Brandt Construction
Milan, IL
LuAva Inc
Park Ridge, IL